# Maintain dates, dependencies and project progress

Investigate schedule contradictions and commitments that cannot be met.

Investigate schedule contradictions and commitments that cannot be met.

## Review the timeline

Product location: `/planner/{planId}/timeline` (fallback: `/planner`)

Open the project **Timeline** and inspect its phases, work items, milestones, owners and dependencies. Check whether a date is calculated or pinned before changing it.

A critical milestone defines a commitment for critical-path analysis. If no milestone is marked critical, the overview has no critical commitment to work backwards from.

## Recalculate and investigate

Product location: `/planner/{planId}/timeline` (fallback: `/planner`)

Use **Recalculate schedule**, then review the overview's diagnostics.

<table style="min-width: 50px;"><colgroup><col style="min-width: 25px;"><col style="min-width: 25px;"></colgroup><tbody><tr><th colspan="1" rowspan="1"><p>Diagnostic</p></th><th colspan="1" rowspan="1"><p>Review action</p></th></tr><tr><td colspan="1" rowspan="1"><p>Dependency cycle</p></td><td colspan="1" rowspan="1"><p>Remove or correct a link in the loop; no schedule can satisfy circular dependencies.</p></td></tr><tr><td colspan="1" rowspan="1"><p>Pinned-date conflict</p></td><td colspan="1" rowspan="1"><p>Decide whether to move the fixed date or change the preceding work. The pinned date is retained.</p></td></tr><tr><td colspan="1" rowspan="1"><p>Over-committed person</p></td><td colspan="1" rowspan="1"><p>Review overlapping assignments and available capacity. The warning does not automatically move work.</p></td></tr><tr><td colspan="1" rowspan="1"><p>Broken link</p></td><td colspan="1" rowspan="1"><p>Reconnect the intended source record or remove the obsolete plan item.</p></td></tr><tr><td colspan="1" rowspan="1"><p>Plan and work disagree</p></td><td colspan="1" rowspan="1"><p>Compare the due date in the owning module with the plan's requirement.</p></td></tr></tbody></table>

## Record progress in context

Product location: `/planner/{planId}/board` (fallback: `/planner`)

Use the Board for work status and open linked records when their completion needs to be recorded in another module. Inspect any manual progress override before interpreting a summary percentage.

Recalculate after meaningful date or dependency changes and check whether the affected milestones are now achievable. A calculation can expose a conflict; resolving it remains a planning decision.